Volunteers from Hai Duong have shared some on-site photos of the unloading and handling of cargo from the MV YUE PING at Pier No. 1 of the Quang Trach Power Center’s dedicated port.

The train carried approximately 73,600 metric tons of imported bulk coal, which was received and unloaded according to schedule to supply the Quang Trach 1 Thermal Power Plant.

MV YUE PING – 73,600 metric tons of imported bulk coal

The MV YUE PING is one of the coal-carrying ships scheduled to support the fuel supply plan in the Quang Trach area in October 2026.

After the ship arrived in the port area, the reception, handling, and unloading operations were carried out as planned at the dedicated berth of the Quang Trach Power Center.

Shipment Information:

  • Vessel: MV YUE PING
  • Cargo volume: approximately 73,600 metric tons
  • Goods: Imported bulk coal
  • Operating Location: Bridge No. 1 – Dedicated Port of the Quang Trach Power Center
  • Serves: Quang Trach 1 Thermal Power Plant

Actual photos taken during the cargo handling process

Images captured directly at the port show the coal being stockpiled in the ships’ cargo holds before being gradually unloaded and received.

From the process of maritime transport to the ship’s arrival at port and the unloading of cargo, each stage is a link in the coal supply chain that supports electricity generation.

Posting up-to-date photos also helps customers and partners gain further insight into the scale of TNV Hai Duong’s inventory, port operations, and its ability to organize supply plans.

Taking the initiative in every supply plan

For thermal power plant customers, the ability to organize fuel supplies and closely monitor delivery schedules plays a crucial role in maintaining the plant’s fuel plan.

Hai Duong Volunteers continues to coordinate activities ranging from sourcing imported coal—sea transport—receipt at the port—unloading—to the subsequent steps in the supply chain, with the goal of ensuring a stable and continuous supply.

TNV Hai Duong will continue to provide updates on ship arrivals, unloading, and production activities in the coming period.

TNV Hai Duong’s System of 5 Ports, Warehouses, Yards, and Factories

TNV Hai Duong is currently developing a network of five ports, warehouses, storage yards, and production plants for anthracite, bituminous, and other industrial coal types, including:

Port No. 1: Chau Xa Residential Area, Nhi Chieu Ward, Hai Phong City.
Port No. 2: Bai Sai Area, Kinh Mon Ward, Hai Phong City.
Port No. 3: Viet Tri Port, Thanh Mieu Ward, Phu Tho Province.
Port No. 4: Thuy Minh, Bach Dang Ward, Hai Phong City.
Port No. 5: Dien Cong, Uong Bi Ward, Quang Ninh Province.

TNV Hai Duong cordially invites our valued customers and partners to visit our network of ports, warehouses, yards, and anthracite and bituminous coal production plants to learn about our product sources, operational processes, and verify product quality firsthand.

Sales Office: BH 06-15 Vinhomes Imperia, Hong Bang Ward, Hai Phong City
Hotline: 092 688 3333 – 096 2211 555

HAI DUONG VOLUNTEERS – Securing a stable coal supply, ensuring project timelines, and supporting production.

SEO Title: Photos of the MV YUE PING unloading 73,600 metric tons of coal at Quang Trach Port

Meta Description: TNV Hai Duong has posted photos of the unloading of approximately 73,600 metric tons of imported bulk coal from the MV YUE PING at Quang Trach Port, to be used by the Quang Trach 1 Thermal Power Plant.

SEO keywords: Hai Duong Volunteers, YUE PING MV, Quang Trach Port, Quang Trach 1 Thermal Power Plant, ship unloading, imported coal, coal supply, thermal power coal, coal logistics.